Content Of The Project
[History of the Keelung River Flood Control]
Year |
1982 ~ 1996 |
1998 ~ 2001 |
2001 ~2005 |
| Project Name |
Taipei Area Flood Control Project |
Keelung River Flood Control Early
Stage Project |
Keelung River Overall Improvement
Project |
| Flood Control Section |
Guandu to Songshan |
Nangang to Cidu |
Nangang to Rueifang |
| Flood Control Criteria |
200-year Flood |
10-year Flood |
200-year Flood |
| Project Brief |
Construction of Dikes, pumping stations,
water gates; straitening of channel
curves; flood forecast system |
River dredging; bank protection;
dike & water gate constructions;
reconstruction of pumping station
bridges |
Yuansantze flood diversion; construction
of dikes, water gates & pumping
stations; reconstruction of bank protection
bridges; water & soil conservation;
flood forecast & inundation alarm
system establishment |
| Notes |
Project completed and in operation |
Completed |
To be completed at the end of 2005 |
Flood Control Measures
Main river flood control construction.
- Yuansantze flood diversion construction.
- Coordinated drainage improvement measures.
- Bridge improvement construction.
- Hillside water and soil conservation measures.
- Flood detention areas.
- Non-constructional measures.

Chart of Designed Flood of Each River Segment Unit: M3/S
Project Benefits
After the completion of the Early Stage Project, it can protect approximately 200 hectares of flooding from 10-year flooding area.
 
|