[History of the Keelung River Flood Control]

Year

1982 ~ 1996

1998 ~ 2001

2001 ~2005

Project Name Taipei Area Flood Control Project Keelung River Flood Control Early Stage Project Keelung River Overall Improvement Project
Flood Control Section Guandu to Songshan Nangang to Cidu Nangang to Rueifang
Flood Control Criteria 200-year Flood 10-year Flood 200-year Flood
Project Brief Construction of Dikes, pumping stations, water gates; straitening of channel curves; flood forecast system River dredging; bank protection; dike & water gate constructions; reconstruction of pumping station bridges Yuansantze flood diversion; construction of dikes, water gates & pumping stations; reconstruction of bank protection bridges; water & soil conservation; flood forecast & inundation alarm system establishment
Notes Project completed and in operation Completed To be completed at the end of 2005


▲ Flood Control Measures

  1. Main river flood control construction.
  2. Yuansantze flood diversion construction.
  3. Coordinated drainage improvement measures.
  4. Bridge improvement construction.
  5. Hillside water and soil conservation measures.
  6. Flood detention areas.
  7. Non-constructional measures.








Chart of Designed Flood of Each River Segment Unit: M3/S


▲ Project Benefits

After the completion of the Early Stage Project, it can protect approximately 200 hectares of flooding from 10-year flooding area.